MM-subcontracting challan

how to make subcontracting challan

replied

Hi,

u use this transection codes with reference to material document

J1IF01  Creating sub contracting Chelan

J1IFQ  Reconciliation for Chelan

J1IF13  after receiving all items

Regards

Rao