on 10-02-2008 6:36 PM
Thanks in advance for your help, and sorry for the seemingly simple question, but I am new to integrated planning.
I am trying to provide a simple method for the end users to update planning data in a cube. From what I read I should be able to do this with a real time cube and an input enabled query.
I have created the real time cube with my desired characteristics and key figures. I have loaded base data to it and change it to be input ready.
Now I need to create my input ready query. I cannot seem to figure out how to do this. From BEx Analyzer the options for enabling input and change mode at query start are greyed out.
Can someone enlighten me on what I am missing or suggest some reading on how to do this?
Regards
KB
Figured it out. Was a matter of selecting the correct type of planning mode for the KF.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK, I got over this hurdle. Turning a KF on for input enable the selection to have the query open in change mode. However, when I do this and run the query in WeBEx the query line style changes to all blue and does not allow input.
I have all my Characteristics from the cube included in the aggregation and have included them all in the query as well (in the same order).
Any thoughts?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pedro, you are my new hero.
This worked mostly. I can now create the query and enable the update option on the key figure.
Can you help further and tell me why the option for opening the query in change mode is still greyed out?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you gone through this link?
http://help.sap.com/saphelp_nw70/helpdata/en/43/1d023a41130bd5e10000000a422035/content.htm
You cannot build your input-enabled query directly on the Transactional Infocube. You need to use a Planning Level.
Go to transaction RSPLAN and enter the Planning Modeler. There you can create a planning level based on your transactional infocube. You can select the relevant characteristics or use all if needed. Then you can create a query, using query-designer and selecting the level as Infoprovider. There you can make it input-enabled.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
10 | |
10 | |
8 | |
7 | |
7 | |
7 | |
6 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.