10-02-2008 6:41 PM
I have edited an existing standard text object (SO10) in DEV, but I do not see how I can transport it to PRD. Are standart text object transportable? If so, how do I do it?
Thanks.
10-02-2008 6:51 PM
Hi,
SE38->RSTXTRAN-->Execute
Name of correction: the transport number you want to transport
Text key - object: TEXT
Text key - name: Standard text which you created in SO10
Text key - ID: ST
Text key - language: EN
Thanks,
Sree.
10-02-2008 6:51 PM
Hi,
SE38->RSTXTRAN-->Execute
Name of correction: the transport number you want to transport
Text key - object: TEXT
Text key - name: Standard text which you created in SO10
Text key - ID: ST
Text key - language: EN
Thanks,
Sree.
10-02-2008 7:34 PM
hey,
I hope u have done..Basis team is supposed to execute the report mentioned....
There is no method to transport them....
I think , even without transportatin, u can directly modify the std text in testing server...just do , if u want to test..it is not advisable