Hello Gurus,

I am trying lock period 1-8 via OKP1 for planning controlling. Then I go to KP06, I call my planning template. I try to make changes just to test on periods 1-8 and it does not allow which is how system is supposed to behave.

But when I try to make changes in period 9 system still tells me that cannot make postings, when I go to error lock it says that periods are closed. When I go back to OKP1 to verify only periods 1-8 are closed.

The template has data from periods 1-8, which I am not changing, I am only making changes to period 9.

Am I missing anything?

Thanks for your help