MRP with reorder point and safety stock and planning calender issue

Hi,

We are using currently MRP type PD and using Scheduling agreements and after the demand management changes when ran MRP the delivery quantities are fluctating in higher range and vendor complains about it so to avoid this we are constantly changing GR Processing days in material master? how can we avoid the drastic changes on the order quantites on scheduling agreements with out changing GR processing days.

For example : we constantly manufacter 480 vehciles per week and some time because of holidays it will be 320 or 560 per week then the forward scheduling agreement quantites instead of 480 parts week(twice a week delivery) goes up and down and vendor needs a at least a range for his prodcution?

I was thinking to use Reorder point but when i changed the MRP type VB then i cannot see forward scheduling agreements at MD04? does MRP type VB or V1 will allow forward scheduling also like 120 days ahead of planning?

Appreciates everyone time and help.

Thanks and Regards,

Siva