Hi

Could you please tell me what concern between Cost Center and Material.

Example: If I purchase a Material. I want to know which Cost Center contain this PO.

Regards,

Thang.

replied

Hi,

If you purchase material to stock, there is no cost centre, as it is about a posting to balance sheet account (stock). When you purchase material for costing, you enter cost centre in the account assignment of the purchase order. There is no direct link between material and cost centre.