on 10-02-2008 8:55 AM
hi. in MCEC what can be the reason why a material doesnt appear in the MCEC long term analysis report, even if simulative requirements have been generated for the material. ( as seen in MD04 ).
Dear,
I'm not sure but MCEC report we are getting monthly report.
for MCEC it uses info structure S012 - 0008 in SPRO it is TC OMOL
LIS reports have selection version so please check it?
Or,
To analyze long term planning, there are different ways:
item : MS05 - MS06 - MS44 - MS47
purchasing : MCEC - MCEA - MCEB
stock - MCB)
Regards,
R.Brahmankar