BOM Usage and BOM Application

Hai,

1) Is there a link between BOM Usage and BOM Application ?

If so, where we can exactly see the link between the two.

2) In Normal Routing (N), I am trying to Allocate Components. When I click on CompAlloc button I got a

Pop-up showing all the possible BOM usages of the Material given (like BOM Usage 1, 5, etc) along

with their Alternatives. I selected BOM Usage 5, but could not see any data for Allocation.

The message in the Status Bar is,

No entry found for the specified filter criterion.

But, when I got to CS03 and display this Material with BOM usage 5, I could see all the components.

What is the reason behind this ?

Thanks

replied

Hi,

In routing header, check up the usage mentioned. Maintain the usage as "3" in this field so that you can get the data as per your requirement.