on 10-02-2008 4:35 AM
Hi,
Need help so as to make the material qty field as mandatory. (when material is attached in proj structure).
hi,
need to check tickbox as Required Entry for qty in PR..
navigate to IMG > Materials Management > Purchasing > Purchase Requisition > Define Screen Layout at document Level
select the field selection key relevent to your projects (NBB for example) then in table for quantity and Price you can put the quantity as required..
hope it helps..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
But in our case, only reservation gets created upon attaching material to the project structure.
So, the settings related to purchasing may not be relevant.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.