Strategy 10, MRP generating unwanted Plan Order from Sales Order

Former Member
0 Kudos

Hi,

Would appreciate some help here.

We have set strategy 10 for the FGS and SFG

There is a reduction in PIR for the FGS every time we do a Post Goods Issue for a Sales Order.

Lately, we decided to sell the SFG in the FGS as spare parts hence we needed to plan the SFG in PIR.

Problem, is that we are getting a double requirement in the Stock Requirement List.

Plan Order will be generate from both the PIR and Sales Order.

We do not want the SFG Plan Order generated from the Sales Order. Further testing shows also that the SFG Plan Order does not consume the PIR at all upon PGI.

Any suggestions? I am really stumped!

Thanks,

Lee

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

i am surprised when this strategy was working so fine for you what happened afterwords.

double requirement can be genrated for SFG since u might not check box(MRP 4 view) do not plan dependant requriement, since you are already putting PIR for SFG, why u want dependant requirement also.

and if you are selling SFG with str 10 in MM then PIR should be reduced after PGI.

Regards,

Pravin Mukkawar

TCS canada

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

First check below points for sub assembly,

1.PIR type is LSF at md62

2. Sale order requirement type =KSL at procurement tab of sale order in VA02.

For planning Strategy 10 the above are standard .

Regards

Pradeep Kumar