Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

RA with Method 07- POC Method on Basis of Project Progress Value

Hi Experts.

Have anyone done the RA with Method 07- POC Method on Basis of Project Progress Value

Have some issue while running RA.

Thanks

PS Consultant

replied

that is correct once the WBS is TECOed then only actual cost will be there as there is more calculated cost requirement and there is nothing to accrue or defer - job is completed no WIP

again the system behaviour is correct as expected

0 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question