on 10-01-2008 2:41 PM
Dear All,
The scenario is described below.
I have a service vendor who is doing some painting work for me,for which i will give only the processing charges(labour cost) and the material(paint) will be provided from my stock.And after completion service entry sheet will bee created as per normal service procurement.How to handle the scenario??
hi
create a cost center for the painting works
create a service po (without material )
and just give charges of painter
for the service process follow the link
http://www.sap123.com/showthread.php?t=52
now for paint consumption u have to issue the paint to the painting cost center
hope it clears
regards
kunal
award if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1. AC01 - Service master AC01
2. ME21N - In PO (ME21N),
Item category as "D" (Services)
Account Assignment Category "K" (Cost Center)
and "Services" tab, specify the Service Master
& pricing details
3. ML81N - Service Entry Sheet w.r.t. Service PO
4. MIRO - LIV Service PO
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.