Subcontracting issue related to BOM

Former Member
0 Kudos

Hi

I created Subcon.P.O.. for material -" MAT001"

MAT001 have alternative BOM's 1 and 2

but when i am creating subcon P.O for material MAT001.. THEN CLICK EXPLODE BOM...system automatically pick the component as per ALTERNATIVE 1...some times i want to pick materials as per alternative 2...how can it possible..?

any body can help me...

regards

sesidhar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

If NO selection mechanism has been defined and several

alternatives exist, the FIRST one found is pulled. !!!!

Please also refer the attached notes

430706 Subcontracting, incorrect alternative BOM determin

205454 Documentation on subcontracting

Answers (2)

Answers (2)

kunal_ingale
Active Contributor
0 Kudos

hi

SAP considers:

lot size (you can define it in CS02)

explosion date of BOM (OPPP)

production version (you have to create infor records, source lists and quota arrangement - and you can assign PV to QA)

http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2aea44af11d182b40000e829fbfe/frameset.htm

regards

kunal

Former Member
0 Kudos

Hi

i think QA is applicable for ..if we have more than one vendors..

we have one vendor for this sub con material.. but this sub con material have 1 and 2 alternative boms

system always taken automatically altnative1..if want to alt 2..add all compents manually in P.O..

I am trying to avoid manual enter..

thanks and regards

sesidhar

Former Member
0 Kudos

In addition to that you can manually put the components by clicking on the componenets push button, in the componenet screen give the componenet material code and the quantity.

Regards

Sujoy