Hi i have created Production order with MTO
When i see the cost analysis, out of 10 material for 2 materials
Total target cost showing 0 Total actual cost and target/actual variance showing the 10$
how to solve this issue
thanks
Dear,
Once you do the GR of that Prod Order and the status will DLV then the Target will show. Run KKS2 and then check your result.In production order or KKBC_HOE
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the price in material master accounting/costing view. Maintain it and read the PP master data again in the production order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.