Where can we maintain manufacturing date and expiry dates in MIGO or during gr

Accepted Solutions (0)

Answers (8)

Answers (8)

Former Member
0 Kudos

answered

former_member192897
Active Contributor
0 Kudos

Please Ensure you have Maintained SLED field in Material Master.

Now When Doing Gr for Material go to Batch Tab in GR and Maintain the Same

JL23
Active Contributor
0 Kudos

if it is batch managed material, then at the batch tab in item detail of MIGO.

Make sure that you maintained the total shelf life field in Material master storage location view.

Former Member
0 Kudos

u can use the item text field for maitaining the manufacturing date and expiry date.

regards,

sujit

former_member581212
Active Contributor
0 Kudos

check BATCH tab

Regards

Priyanka.P

Former Member
0 Kudos

Dear,

You can maintain it in the tab of Batch in MIGO.

First you have to enter Vendor Batch and Manufacture date.

With reference of manufacture date your expiry date will be automatically calculate from Total shelf life Data of material master Plant Data/Store 1 view.

Regards,

Mahesh Wagh

Edited by: Mahesh Wagh on Oct 1, 2008 12:59 PM

Former Member
0 Kudos

Hi

MIGO is the T- code used for Making

a GR and GI.....

so you can enter both these dates

in MIGO.

thanks

prasanna

awrd if usefull

former_member529134
Active Contributor
0 Kudos

Hello

You can maintain the date of manufacture in the Batch tab in detail screen in MIGO.

Maintain the shelf life in the material master.

Regards