on 10-01-2008 11:34 AM
Hi All,
How to make default that PR/PO for project/wbs belong to NB. I only can find for network..not for WBS.
Please help.
Cheers,
Nies
Dear Nies,
You can't create consumption PR on WBS thru' cj20n. only network PR u can make on network in this regard you can make a default NB document thru' OPTT.
You can create manual PR(ME51N) thru account asst. "P" and maintain defaut thru' ME51N personal setting.
Click on personal setting Tab.
Click Default TAB then choose Doc. type.
Hope it will give u help.
Regards,
Vishal Kr. Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in transaction OPTT you can set for network (order category 20)
you cannot default for WBS
if you are using networks then you should not raise PR/PO from WBS anyway
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.