How to Make a default PR/PO for Project/WBSE belong to NB

Former Member
0 Kudos

Hi All,

How to make default that PR/PO for project/wbs belong to NB. I only can find for network..not for WBS.

Please help.

Cheers,

Nies

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Nies,

You can't create consumption PR on WBS thru' cj20n. only network PR u can make on network in this regard you can make a default NB document thru' OPTT.

You can create manual PR(ME51N) thru account asst. "P" and maintain defaut thru' ME51N personal setting.

Click on personal setting Tab.

Click Default TAB then choose Doc. type.

Hope it will give u help.

Regards,

Vishal Kr. Sharma

virendra_pal
Active Contributor
0 Kudos

Vishal - good idea with the personal settings suggestion

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

in transaction OPTT you can set for network (order category 20)

you cannot default for WBS

if you are using networks then you should not raise PR/PO from WBS anyway