My client senario is PP-PI. Order confirmation is against PI sheet. The main issue is that they want by-product auto confirmed ( comes in QI stock ) during PI sheet confirmation.
What settings I have to do to fulfill this requirement. Please let me know.
Thanks and Regards,
Harriesh.
Hi,
Only the Main Product are confirmed and not the By-products.
By-products are entered in the BOM with a negative quantity. Only the main product are confirmed and Goods receipt is done by movt type 101 and the components issue is done with movt type : 261 whereas the By-products are done GR with the Movt tyoe 531.
regards
radhak mk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I start with believing that you have maintain -ve Sign in BOM for that By Products.
You can confirm GI of Components,GR of Header material and By Product (Movement type 531) thorough PI sheet.
- Use Process Message PI_CONS for both Components and By Product.
- Use Process message PI_PROD for Header material.
Activate Post to QI stock in QM view of material master for that By Product.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can't confirm your By-Product, only main product can be confirmed.
You can confirm the Co-Product.
Regards,
V. Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.