MRP generating purchase requisition

Former Member
0 Kudos

Hi Gurus,

I have a FERT material say A, and below which i have a ROH material . There is a variant created for background job of MRP, which is running once in a day.in this varaint , i have control parameters set in such a way in that , it should create

planned orders for ROH not purchase requisition ( "PURCHASE REQUISITION" 3 ) . But its creating purchase requisition only.

In OMD1 T-code "Purchase requisitions" i have fixed 3 ( planned orders), even then , the system is creating purchase requisition not planned orders.

Please help me creating planned orders instead of purchase requisitions.

Regards

Kaisar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Go to MDBT click on your veriant and check the indicator for Create PUrchase Req. : 3- planned order.

In this variant you will get radio button for attributes make it fix value.

Then Define Scope of Planning for Total Planning in 'OM0E'.

Then check your result.

Please rfer this for background MRP

http://www.sap-img.com/pp019.htm

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

In MRP 3 maintain procurement as a in house production.

Thanks

Raja.