PP-PI confirmation

Dear Friends

we are working on PP-PI ,,

we created process order for 100 qty which has 3 operations..

During operation confirmation -COR6n..

In The first operation/Phase we confirmed yied as 90 and scrap as 10..

when we are going to confirm next Operation/Phase.. system is poping for yield qty to confirm as 100.

My end user wants system to pop up for 90 as he confirmed for the last operation yield 90 only..

we are using operation control key --Process confirmation without Inspection with confirm..

What are the setting required to do the above..

regards,

srihari.m

replied

Hi,

Try it again by below settings,

- Maintain relation between Phase 20 and 30 and FS Means Operation 30 will be started only after completion of Phase 20.

- Then create Order for example of 100 qty.

- Confirm Phase 20 with yield of 95.

- Confirm Phase 30 as below

1 Select Order no and Phase No.

2 Press actual Data tab.System will propose 100 Qty for the confirmation.

3 Then select Personeel no. for the confirmation.

4 Then again press Actual Data tab.System will change yiled qty from 100 to 95.

Regards,

Dhaval