While run MRP

Hi PP/MM guru

I have one raw matrial which is having three vendor. While running the MRP I need vendor based lead time . But MRP does not taken into consideration .

For Example

Materail Rod (Raw materials) which has following vendoars

Vendor A , Lead time 45 days

Vendor B,lead time 10 Days

Vendor C , lead time 5 days

But MRP leadtime in Material master 20 days

Requirement is while run the MRP i need lead time vendor based not MRP based

Can any one tell me the solution

regards

Sam