on 10-01-2008 7:26 AM
Hi PP/MM guru
I have one raw matrial which is having three vendor. While running the MRP I need vendor based lead time . But MRP does not taken into consideration .
For Example
Materail Rod (Raw materials) which has following vendoars
Vendor A , Lead time 45 days
Vendor B,lead time 10 Days
Vendor C , lead time 5 days
But MRP leadtime in Material master 20 days
Requirement is while run the MRP i need lead time vendor based not MRP based
Can any one tell me the solution
regards
Sam
thanks all for your valuable input
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Planned Delivery Time are maintained in 3 places
1)In Material Master, MRP 2 View
2)In Vendor Master, Purchasing Data View
3) In Info Record, Purchasing Org View
In Material Master, MRP View what you are maintaining....based on this thing only, the "Replinshment Lead Time" of MRP Planning is calculated...( RLT is nothing but PR Processing time + Planned delivery Time + GR Processing time)
In Info Record What you are maintaining, it will be copied to PO
Planned delivery time in maintained in Inforecord/scheduling agreement,material master and vendor master
If u have activated it in OMDT for plant level planned delivery time is always calculated from info record/scheduling agreement acoording to your vendor.
Or,
It is possible if you run MRP for vendor in MDW1 by activating MRP Area
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.