Doc Date displayed on PO is not correct.

Former Member
0 Kudos

Purchase order was created on 28-Sep but while creating purchase order wrongly enter date as 29-Sep.This PO was created yesterday with today's date.

PO dated is printing date before. On Sept 28th, the PO printed Sept 29th.

It is possible to change Purchase order document date.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

Once Purchase Order is Saved you cannot Change the Document date, Document type & Vendor Etc Fields.

You have to cancel that Purchase order and make a new Purchase order.

Regards

Manish Joshi

Answers (2)

Answers (2)

former_member192897
Active Contributor
0 Kudos

Once Purchase Order is Saved you cannot Change the Document date, Document type & Vendor Etc Fields.

Former Member
0 Kudos

Dear,

It is not possible at transaction level.

If you have major problem about it then contact your Basis person one function is available for table change.

Regards,

Mahesh Wagh