cancel
Showing results for 
Search instead for 
Did you mean: 

Commitment in Report

ansar_shaikh2
Contributor
0 Kudos

Hi PS Gurus

Iam having one issue in my support project, In Report S_ALR_87013533 this report is not showing commitment - material against network activity, but showing network activity, so plzz tell me how to view the commitment of material.

plzz help me out

Regards

Ansar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The GL account code that is being determined in procurement for the material should be created as 'statistical cost element'. Ask FI person to create this. Once this is done, you will automatically see commitment value. This is as per standard SAP. In case yoiu do not get this value as commitment, please rebuild PS infor data base once using transaction CJEN.

Regards.

Answers (2)

Answers (2)

ansar_shaikh2
Contributor
0 Kudos

thanx

Former Member
0 Kudos

Hi,

I think something may be wrong in your configration or PR/PO.

Pls. check thease following points:-

1. Check SPRO-Project sysyem-Costs--Activate Project Management in Controlling Area---Commitement Management active in Controlling area.

2. Check the G/L should not be Balance sheet nature in PR/PO.

Hope it will give u help.

Regards,

Vishal Kr. Sharma