Flexible planning

Former Member
0 Kudos

Hi gurus,

In SOP I want to map a scenerio where in I have created my own infostucture as S999 with required key figures.When I am trying to create plan with inactive version using the newly created infostructure the values are not being saved and the message is displayed as 'Plan saved under version xxxxx'.I am not able to proceed furthur coz of this error.What could be the possible reason for this error.kindly guide me through so that I can create plan and then transfer this to demand.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

What is the message number?

You need to convert paln to active version:

LOGISTICS--> PRODUCTION --> SOP --> PLANNING --> FLEXIBLE PLANNING --> PLANNING --> VERSION MANAGEMENT --> MC8V - COPY

Transfer to Demand management:

LOGISTICS--> PRODUCTION --> SOP --> PLANNING --> FLEXIBLE PLANNING --> Enviroment --> MC90-Transfer material to Demand Management

When you create the planning type MC8A you will get a pop up for the information structure there you need to give S999.

Regards,