Hi Friends,

1. In Work Centre : In the capacity tab and fields inside when we give shift timings and length of breaks system proposes the capacity in MIN , which means for it to work those many MIN are available

we require to enter the capacity of the conveyor in Number of parts made on it for example no.of vehicles producing capacity of the conveyor

for our report development purpose we need to have it . As different conveyors have different production capacities , we can not take this available time as it comes same for all

is there any field in creating work centre where we can input and store the capacity of that conveyor in terms of production .

2. Similarly in routing we have say 10 sequences , among those one is main line operations , few are of subassembly operations and some are of inspection operations

for developing report we need to seggregate these sequences in to three categories and some where in the sequence we have to mention that this belongs to thsi category ( categories are main line , sub assembly , inspection )

can i have some helpful inputs on these

requirement is while entering a sequence its description we shoudl be able to flag it as either mainline operations sequence or sub assembly operations sequence or inspection operations sequence

how to address this ?

regards,

madhu kiran.

Former Member