MRP run for MRP out put -reg

hi friends,

our requirement is like this .

we have two plants A and B in different company codes.

plant A will procure some parts and supply to plant B , it supplies both parts procured from suppliers and also assembly parts

the lead time for parts supply between plants is one month .

now when MRP is run for plant B it gives the requirements at plant B , based on these requirements plant A should procure materials and produce Assemblies and send to Plant B against the required date

how system can be set to address this issue?

for example

plan is put at plant B for the month December , requirements will come at Plant B against the requirement dates in DEC .

Since lead time between plants is one month ,plant A should procure these parts required at plant B by November and supply to plant B .

for procuring the parts from suppliers by Nov , shall we again run MRP for these parts at plant A ,procure materials in date and supply by required date at plant B ?

for these what system settings are to be done ?

if any other solutions are there also please let us know

regards,