on 09-30-2008 8:25 PM
Hi Gurus,
I am having two plants defined in one company code.
Is Planned order number range plant specific?
My planned order number range in plant-1 is 1000-2000 and it is same in the Plant-2. If I create the planned orders in both plants.
What is starting number for planned orders in each plant?
Can I create like this?
Thanks in advance.
Regards,
Jejesh
Edited by: jejesh yal on Sep 30, 2008 9:25 PM
Dear,
Yes you can create the plant specific number range in MD91then assign to your plant in OMI2 or OPPQ.
Please try and come back.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
If you are creating Planned order using the MRP, you can set the plant specific Number range for planned Order at OPPQ
Please check with planned order Number range tab at OPPQ
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.