Hi Gurus,

I am having two plants defined in one company code.

Is Planned order number range plant specific?

My planned order number range in plant-1 is 1000-2000 and it is same in the Plant-2. If I create the planned orders in both plants.

What is starting number for planned orders in each plant?

Can I create like this?

Thanks in advance.

Regards,

Jejesh

Edited by: jejesh yal on Sep 30, 2008 9:25 PM

replied

Dear,

Yes you can create the plant specific number range in MD91then assign to your plant in OMI2 or OPPQ.

Please try and come back.

Regards,

R.Brahmankar