on 09-30-2008 4:52 PM
Hello...
gettting the below error that while generating InterCo. billing.
"No WBS elemant found while substituing WBS element"
but on the other hand no such error is coming while creating F2.
I donn know may be due to different Cocode.(since error is coming in IV only).
is something needs to be done at WBS element or SD side???
pls suggest..
Thnx in Advance
Hi,
In case of IV WBS should get copied from PO.
Goto PO and check if you have input you account assignment category as "P".
If yes then goto account assignment tab in PO line item and check the WBS element which you have put.
The same needs to get copied in billing document.
Regards
Karan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Hari,
This error due WBS element not entered in the preceding documents of the IV.
The material which you are consider in the inter company process it may related to the Project item.
So please enter the WBS element data then try
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.