setting Float before production (in day)

Former Member
0 Kudos

Hi,

How can I set the Float before production (in day) in Material master and in the BOM?

Thanks

Dede

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Schedule margin key includes,

1. Opening period

2. Release period

3. Float before production

4. Float after production.

Opening Period: It is the time to MRP controller to convert planned order to pur req.

For FERT & HALB opening period, release period, Float before production & float after production are applicable.

But for ROH only opening period & release period only applicable.

You need to assign schedule marging key in material master MRP2 view.

For Customizing for Shop Floor Control, by choosing Operations --> Scheduling --> Define Scheduling Margin Key .

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

this is done through schedule margin key(SMK) in MRP2 view. This can be configured in SPRO. Just check Shop floor control-operation-schedulling-define schedule margin key.

Edited by: BNR on Sep 30, 2008 4:17 PM