Whether a project with status TECO can be released

Whether a project with status TECO can be re-changed and once again used for planning.If not who will have authorisations to re-use it.

We have closed a project for which the resources and WBS has been planned. Now we want to continue with the same project. Please let me know if it is possible...?

Former Member
Former Member replied

Hi,

you can revert the project statuses as given below.

T-code-CJ20N

Edit-> status-> Close-> undo

Edit-> status-> complete technically-> undo

Regards

Sophia