on 09-30-2008 2:40 PM
Whether a project with status TECO can be re-changed and once again used for planning.If not who will have authorisations to re-use it.
We have closed a project for which the resources and WBS has been planned. Now we want to continue with the same project. Please let me know if it is possible...?
Hi ,
TECO is the operational closure of any WBS ar Activity if we put a status against any WBS any operational work like Purchase order,production order cant be done against it.
CLSD Closed status is financial closure of the WBS or acticvity.
Both these status can be reversed if required depends on the authourisation provided to the user.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chandra,
if you have closed the project then first reset closed status by
following path .
CJ20N---->EDIT->STATUS--->CANCEL CLOSED.
then project will come on TECO status if u have first set TECO
to reset closed Technocally follow
EDIT->STATUS->CANCEL CLOSED TECHNICALLY.
then system Status will be RELEASE.
Then Save.
Hope this will solve Your Problem.
Regards,
Vivek Tripathi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Status TECO can be reset.
Edit -> Status ->Complete technically ->Undo
With this the project will go back to REL status.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.