Hello,
we have an ERP-system (DEV, QA, PROD) and want to activate the transport workflow.
At the moment we have the Transport strategy "Mass transports" and a job (TMS_0000000003TMS_TP_IMPORT) is running (every 15 min.) on the DEV system which transport and import all transports in the QA-system.
At the QA-system we have the Transport strategy "Mass transports" with Quality assurance "Delivery after confirmation" activated, because the transports have to be approved by a system administrator for the PROD-system.
So when we will activate the transport workflow we want that the transports are still transported and imported from DEV to QA system without transport workflow and only from QA to PROD system we want the transport workflow.
Is there a possibility to configure our requirements or is there a workaround ?
An another question about the transport workflow. Is there a possibility to affect only time slots for the import in PROD system ?
Thanks in advance.
Best Regards
Carsten
Hi,
As per your quer you can not define workflow from QA to PRD.
Anil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.