Hi All,

From where system picks Scheduling start & finish date & time in order.

regards

sunil

Accepted Solutions (0)

Answers (3)

Answers (3)

MTerence
Active Contributor
0 Kudos

Hi Sunil

When u create a order, the start date will pick the order creation or u can specify the date start date

For scheduling, you have to define forward or backward in the customizing. so it picks from there.

- pithan

Former Member
0 Kudos

HI

based upon the routing or task lsit opearation hours the system caliculates the time.

and your work centre workning times

when the order is called based on scheduling the start time comes to the start date and time the routing hours are added.

with this the end date and time comes in order.

-ashok

former_member220863
Active Contributor
0 Kudos

Dear All,

I have created one work center.shift start 8am to 20pm , break 1hr , capacity 1 and capacity utilization 100%.

Now i created the order for new work center with one operation for 1hr but my scheduling start time is from 9am and scheduling end time is 10:0am . But as per the work center shift timing,it should be from 8am to 9am.

Why so.How could i get the right timing?

regards

sunil

former_member192718
Active Contributor
0 Kudos

Dear Sunil,

Once select forward scheduling in your order then see.

Regards,

Kaushal Rai

MTerence
Active Contributor
0 Kudos

Hi

Check whether u have maintained the tick for automatic scheduling

- Pithan

former_member220863
Active Contributor
0 Kudos

Dear ,

Yes. Will it make any difference? But i have solved the pblm.

regards

sunil

Former Member
0 Kudos

Hi Sunil,

Timings r taken as per the shifts defined in the work center which you use in the operations.

regards

pushpa

virendra_pal
Active Contributor
0 Kudos

in addition also check config in OPU7