Work clearence management *Performing Lockout/Tagout*

Hai ,

Please help me in getting the following steps---

I am trying this by taking the example from help.sap.com 4.6c and trying to do this in ides ECC 6.0 as I am not having ides 4.6c I taken same master data also.

In Work clearence management , Help.sap.com in the following link example given for ides sap 4.6c --

http://help.sap.com/saphelp_46c/helpdata/en/fe/67ec5c9d6f11d189b60000e829fbbd/frameset.htm

I could not able to get the following steps ,for the same example given in Ides Ecc6.0

Performing Lockout/Tagout

4.Choose . ( not able get this symbol in ECC6.0)

5.Choose .

6.Select Tag.

7.Choose Tag.

Now print out the task list for performing tagging.

8.Choose Process ® Print ® Tagging list.

Tagging carried out on location is confirmed in the system.

9.Choose Tagged.

10.Choose .

The color of the traffic light indicator for the permit switches to green.