Good day!
Here's our scenario: we have created a PR for sub-con service. Then we created a contract with reference to this PR. Then proceeded with the PO and Service entry. After that, we discovered that another contract can be created using the same reference PR. We don't want this scenario. What the client wants is that once a Contract already exist for a PR, there can no more be another contract of the same PR number. Is there a way we can block or avoid this scenario from happening?
Thank you.
Hi,
You have to create a contract from the PR for the Fully Qty.
If the Contract is made from the P.R for Partial qty then you can create another contract for the remaining P.R.
E.g -Material AAA
P.R qty - 1000 Nos
Contract created for 500 nos -Contract ino :20000 00001
For the remaining
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You have to create a contract from the PR for the Fully Qty.
If the Contract is made from the P.R for Partial qty then you can create another contract for the remaining P.R.
E.g -Material AAA
P.R qty - 1000 Nos
Contract created for 500 nos -Contract ino :20000 00001
For the remaining qty you can create another contract
Please try to create contract for the Full qty Problem solved
G.Ganesh Kumar
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.