Work Center capacities and scheduling

Hello,

I would like to ask about the involvement of the work center Capacities and Scheduling, set there is maintain in the Set-Up Formula and Processing Formula. how does it affect the production order finished date?

Please explain.

Thanks

replied

Dear,

First we defined the activity in Standard value key then these activity are use as parameter in formula in work center like set up, machine. Then this work center is assigned to routing where we maintain the timing for this activity. When we create the production order system use the timing from the routing and formula from work center to schedule the order and capacity required to produce certain quantity of material.

Hope clear to you.

Regards,

R.Brahmankar