Former Member
0 Kudos

Dear SAP PM Experts !

How to create a new workcentre .

regards,

A S

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

use t code IR01 to create new work center

regards

thyagarajan

Answers (2)

Answers (2)

peter_atkin
Active Contributor
0 Kudos

AS,

[Work Centre Creation|http://www.4shared.com/file/11066166/2ff74ba7/work_centre_creation.html]

PeteA

Former Member
0 Kudos

Hi

1.use t-code IR01

2.enter the name of WC and plan and teh category

3.enter the description , person responsible andstandar value key

4.default value if require only (control key)

5.Capacities , if WC reklted to machine enter the machin formula and enter the timings of working, available capcity,number of capacities.

6.schedulung

7.costing- enter the activites related workcntre aling with formulaes and also enter the cost cntre related to work center

and save

http://help.sap.com/saphelp_47x200/helpdata/en/d7/45f364b10811d2a5e30060087a7a74/frameset.htm

-ashok