Re: P.O. is picking tomorrows date.

HI guru's,

While generating a P.O. it is picking the delivery date in advance i.e., if I prepare a P.O. on the current date its delivery date is auto displaying as tomorrows i.e., for 30.09.2008 it is picking 01.10.2008 where to correct this.

replies awaiting.

tuljasingh.

Former Member
Former Member replied

Dear,

It is pick from material master.

Check MM03, enter your material code.

Go in MRP2 data, Plant Delivery Time.

If you maintain 3 days as plant delivery time and purchase order is create in current date, then system calculate purchase order delivery data as 06.10.08.

If you want to remove it please remove plant delivery time from material master and if you have to change delivery date then change plant delivery time from material master, you can also change delivery date from purchase order.

Regards,

Mahesh Wagh