on 09-30-2008 5:55 AM
Hi All,
I have an issue on cost splitting.If we have a cost centre of Rs 1,00,000 with three activity types. How can we split the above amt to these activity types?
Thanks in advance.
Regards
srikanth rvs
Hi!
One way for splitting this amount to different activity types is you can prepare assessment cycle to assess this cost to all your work center as per activity types. You can select one base and according to that base you can assess the amount.
You can prepare assessment cycle through KSUB (Plan Assessment Cycle) and KSU5 (Actual Assessment Cycle). This would be generally your one of month closing activity.
Hope it will help. Pls get back to me further clarity.
Thanks & Regards,
Taral Patel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.