MRP

hi experts,

I have created Schedule agreement and quota arrangements for material xxxx with vendor a,b,c

And my indirect requirement is Example-1000 ea

My stock is zero

While running MRP-MD03 it proposed PR only

Actually i plannd for schedule lines

how to do config

or i need to set in MRP parameter intial screen of MD03

explain in detail steps

regards

jai

replied

hi,

Either you use source list or quota arrangement....

For quota arrangement,

Check the Quota arrangement usage field in the purchasing or materials planning in material master record.

Prerequisite for Quota Arrangement is Purchase Info Record and Source List must exist for the material.

Pls check...

Regards

Priyanka.P