MRP
hi experts,
I have created Schedule agreement and quota arrangements for material xxxx with vendor a,b,c
And my indirect requirement is Example-1000 ea
My stock is zero
While running MRP-MD03 it proposed PR only
Actually i plannd for schedule lines
how to do config
or i need to set in MRP parameter intial screen of MD03
explain in detail steps
regards
jai
Priyanka Paltanwale replied
hi,
Either you use source list or quota arrangement....
For quota arrangement,
Check the Quota arrangement usage field in the purchasing or materials planning in material master record.
Prerequisite for Quota Arrangement is Purchase Info Record and Source List must exist for the material.
Pls check...
Regards
Priyanka.P