hi experts,
I have created Schedule agreement and quota arrangements for material xxxx with vendor a,b,c
And my indirect requirement is Example-1000 ea
My stock is zero
While running MRP-MD03 it proposed PR only
Actually i plannd for schedule lines
how to do config
or i need to set in MRP parameter intial screen of MD03
explain in detail steps
regards
jai
hi,
Firstly use the indicator for the generation of the schedule line in the MRP parameters....
Then make your schedule agreement FIX in the source list...this will cause the generation of SA lines when the MRP will run...
Hope it helps...
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
After creation of Scheduling Agreement.
Maintain the Source list in ME01 with Vendor & Plant then input the Scheduling agreement number and the MRP as 2.
Then System automatically display the Schedule lines in MD04 -Stock requirements list.
No need to run the MRP for that Material in MD02/MD03
Hope you got it.
Source list is required here to get the Schedule lines.
rgds
GSC
hi,
no need to run MD03 for this case
thanks and i go and try this
and one more thing for the above case i generated PR ,
but quota arrangement not affected why
it should follow the quota arrangements right
i set vendor 1=50%
vendor 2=30%
vendor 3=20%
but in Pr there is no Vendor name still it remains blank
why
thanks
jai
hi,
Either you use source list or quota arrangement....
For quota arrangement,
Check the Quota arrangement usage field in the purchasing or materials planning in material master record.
Prerequisite for Quota Arrangement is Purchase Info Record and Source List must exist for the material.
Pls check...
Regards
Priyanka.P
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.