on 09-29-2008 6:12 PM
Hello SAP Gurus, I need a litle help,
I have created a SOP in transaction MC87 for a material/plant with quantity 100 for month 10. Then I make a copy to Demand Management and in MD04 I have the requirements. So far so good.
The problem is: when I change the quantity in MC88 for the material/plant to 0, the system doesn't copy to demand management the 0 quantity.
Is there any way to put this to work this way or do I have to go in MD61 and delete the requirements for the material/plant?
Thanks in advance,
Adelmo Silva
Dear,
MC74 is used to transfer the plan for an individual material to demand Management. or try with MC88- Extras--Tranfer to Demand Mangement. Then check your result in MD61.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello again,
I still have the problem...
Can someone please help me with this?
The procedure in the link: [http://docs.google.com/Doc?id=dchkznvw_17c2853bc5|http://docs.google.com/Doc?id=dchkznvw_17c2853bc5]
In SAP R/3 4.6c I dont have this error!!!
Thanks in advance,
Adelmo Silva
Edited by: Adelmo Silva on Oct 24, 2008 12:25 PM
Hello again SAP friends,
Maybe I can explain myself beter:
SAP v4.6C
1. MC88 - I change de Rough-Cut Plan for my material/plant with production values equal to 0 (zero).
2. I transfer to demand management and everything works fine!
SAP ECC 6.0
I do the same as SAP V4.6C and I get the error: "No data maintained for material ARS_PA_01 plant 1000 in transfer period Message no. MA640"
Can someone help me with this?
Thanks in advance,
Adelmo Silva
Hi Silva,
Can u let me know what is configuration missing in S076 as I got the same error message as below.
SAP ECC 6.0
I do the same as SAP V4.6C and I get the error: "No data maintained for material xxxxx plant xxxx in transfer period Message no. MA640"
Can someone help me with this?
Regards,
Patil
HI,
Look at the parameters that you use ( time period) while executing the demand transfer to PIR. You don't need to deleter PIRs manuallly if the forecast is deleted for that time period.
cheers
Rav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please try below path
MC88-> Extras->Tranfer to Demand Mangement.
Regards
Pradeep Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.