Hi Gurus,
While calculating the overheads on network using tcode CJ45, the base in cost sheet calculation were taken for cost element used for booking timesheet. Now when I need to extend to some primary cost elements then system do not consider it at all. Please suggest the possible customization to check. Or what should be done to add more cost element in base of the costing sheet.
Thanks,
Damodarasai
Dear,
You can add the cost element in OKB9
Go to OKTZ t code and add this cost element to your cost component structure and save.
Also see note 75980 for further information.
Components
EXIT_SAPFGRWE_001
EXIT_SAPFGRWS_001
Regards,
R.Brahmankar