Automatic Extrapolation of Basic Date to WBS

Former Member
0 Kudos

Hi,

What setting to be done in SPRO, So that everytime scheduling is done, basic dates are extrapolated to higher level WBS element and to next level WBS with "Open Planning Scheduling Metod". Adjust Basic Dates is selected.

Thanks,

Rahul

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

i am not sure if there is any cofig that does that

you can try bottom up planning with automatic scheduled on so that the dates get extrapolated on project save