Vendor Evaluation using Factory Calendar?

Hello,

Can I set up Vendor Evaluation to consider the Factory Calendar when scoring with the Standard Delivery Date Variance?

I have set it up to allow the delivery to score 100% of the points if the delivery is in by 6AM the following day. But this does not work over the weekends.

Thanks,

Matt

replied

please see OSS note 806832 - Calculation of score for On-time Delivery