Hi,

If I create a PO & save, then i will add a freight condition in PO, will it be activated in version managment.

Also can we configure the fields which we want for triggering the Vesrion management.

Pleae suggest.

Thanks

SHP

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

[Version Management| http://help.sap.com/saphelp_erp60_sp/helpdata/en/8a/60b43bb7492147e10000000a114084/content.htm];

In the case of procurement transactions extending over a longer period of time (for example, in the procurement of capital goods), you may need to differentiate between various versions of the purchasing document. You may also need to refer to one particular version when corresponding with the vendor.

The Version Management facility enables you to generate and manage versions of purchase requisitions and external purchasing documents such as POs. A version groups together the change documents generated in the course of subsequent processing of the relevant document. A version thus indicates the revision level of a document (version 0 = original document, versions 1 + = revisions) and provides the user with an overview of the various changes that may have been made in the course of time.

Version Management thus represents an extension to the hitherto existing change documentation functionality for internal and external purchasing documents.

Version Management can be used in connection with purchase requisitions (ME51N, ME52N and ME53N only), RFQs, purchase orders, contracts, and scheduling agreements.

The following prerequisites must be satisfied before a version of a purchasing document can be deleted:

The changes made in the version must have been reversed (cancelled, revoked)

All open messages must have been deleted

CONFIGURATION:

1) Go to SPRO-MM-Purchasing-Version Mgmt-Setup Version Mgmt for External Documents

Activate Version Mgmt against your Doc type and Double click on that Doc type NB then in next screen in Control data tab mark all the fields and in Field Selection set all the Fields as Required entry Except Posting Date and save.

2) go to SPRO-MM-Purchasing-Version Mgmt-Define Reasons for change

Create one New Reason Called Xyz something and give text and save.

3) Go to SPRO-MM-Purchasing-Version Mgmt-Set up change Displays

Here Select Doc type say NB and Give Table name say EKPO for PO and EBAN for PR, Give Field name say MENGE for qty and save.

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear,

Yes any changes made to purchase documents will be activate version management. Subject to the version management settings done in customizing.

Secondly, as far as I know version management update basing on specific fields update is only applicable to Purchase requisition only. Not possible for external purchase documents.

Regards,

Syed Hussain.

Former Member
0 Kudos

Hi,

You can trigger the Vesrion management based on a Doc. type and purchase organization combination but not on a particular field

byr

aMit

former_member190537
Active Contributor
0 Kudos

Hello

No need to set up fields for Version here..

SPROMMPurchasing--Version management-Set of version mangement for External documents.

Mahesh