on 02-03-2006 12:49 PM
I installed a test system that was at SPAM 620/0008 level. In looking for patches for SPAM, I found packages 0009 through 0019. I chose 0019, imported it and declared victory. Then, as a test I tried to import package 0018. It told me that this package is obsolete.
Are packages in SAP always cumulative? Is the best practice to work forward, one package at a time, or jump to the end and apply the latest one only? Or define them all to the queue manager in SPAM and let them all rip at the same time?
Thanks,
Tim
Only SPAM are cumulative. Rest of the packages like BASIS, ABAP, BW etc. you have to apply them one by one. If you try to apply a later one it will not let you do that, thats beacuase SAP defined the dependencies and they are stored in a DB. when you try to apply a package it reads the DB and checks the dependencies.
regards
Shravan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.