on 09-29-2008 1:31 PM
Dear Experts,
Some of our projects allowed cost assignments even when the budget is not sufficient.
We have a situation as below..
Overall budget - 30,000/-
Overall Commitments - 10,000/-
Overall Actual Costs - 22,000/-
Available Budget - (2,000/-) negative value.
I guess somebody might have Deactivated AVAC using CJBW and again activated using CJBN.
Now Can I be able to Trace whether AVAC was deactivated, through any Transaction,Report or Tables.
Thanks in Advance,
Pravin
Hi Pravin,
The best process is to lock the WBS from Account assignment and then deactiviate and then activiate it back.In order to trace you can check the change documents ....
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi pravin,
Sorry -- i think ther is no change docs for that ... and there is no system status getting updated for WBS / Project when avialability control is activiated and deactivated also....
One way to have view for changes to any fields is goto se11 and enter table name and for each field you can maintain change documents -- tick mark and you can view logs SCU3 by entering the table .... so plz check which tables and fields are updated when u run CJBW ,CJBN .... and proceed
regards
pushpa
Dear Praveen,
You can see these type of History on WBS by following way
1-Doble click on WBS
2-Click on icon 'i'(system/user status).
3-then click on EXTRA>CHANGE DOCUMENT>ALL
4-Then put cursor on system status and click on History Tab.
then u will get all history.
Hope this be useful.
Regards,
Vivek tripathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.