Availability Control

Dear Experts,

Some of our projects allowed cost assignments even when the budget is not sufficient.

We have a situation as below..

Overall budget - 30,000/-

Overall Commitments - 10,000/-

Overall Actual Costs - 22,000/-

Available Budget - (2,000/-) negative value.

I guess somebody might have Deactivated AVAC using CJBW and again activated using CJBN.

Now Can I be able to Trace whether AVAC was deactivated, through any Transaction,Report or Tables.

Thanks in Advance,

Pravin