Help me with the procedure to convert planned order into production order.
Regards,
Srini.
Dear,
Go to MD04 click on planned order at bottom you will get option convert planned order into production order.
Or ue can also use CO40 for convert planned order into production order.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
we can create manually by using CO40 - From Planned Order
and then from MD04 youcan
but there are some prerequisites
1.USe MRP group
2.MRP group -IN OPPR the convert planned ordeer setting should be there
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.