cancel
Showing results for 
Search instead for 
Did you mean: 

activate MRP

sankarn
Participant
0 Kudos

Hi

Should i activate MRP after i upload master data to production or before that

Thanks

Sankar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

MRP activation is the configuration data.

So first activate the MRP then upload the master data.

If u want to activate the MRP in the configuration in production system then its not possible.

Because its not right practice to do the configuration in production .

U should do in the development server then transfer it in to production with transfer request.

Regards

Vijay

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You have to first configure following;

first u need to activate MRP for the plant in the tcode OMDU

then u need to Carry Out Overall Maintenance of Plant Parameters in the tcode OMI8

then u need to carry out Carry Out Overall Maintenance of MRP Groups in OPPZ .

then u need to have activate MRP view in material master for that plant.

enter the mrp type andd enter the details for the selected MRP type.

u can run mrp using Total Planning (MD01)

So check in tcode MD21 whether any planning file entries exists befor you run MRP. Manually create Planning file entry in MD20.

Regards,

R.Brahmankar