material document-quantity adjustment

hi

We made STO for10 quantities, created delivery note for 10, did picking and PGI for 10 qty. GR was done for 8 quantities. now we need to bring remaining 2 quantities back from stock in transit to issuing plant and storage location.

How to do this, any ways? kindly check.

regards

fozters