on 09-29-2008 11:36 AM
Dear Experts,
Can you please explain what is deadline handling in workflow?
Usually workflow goes to a set of approvers.
But when the deadline is reached , it workflow goes into inbox of
completelty different approvers.
On what basis is this done and why is this done?
Can you explain in detail as im new to workflow..
Thanks in advance
SS
Hi,
Dead line monitoring is used to notify approver about deadline of task.
If you set deadline against your approving task for particular date for e.g. leave request WF.
If you want to monitor it and want to give alert via mail you can do it by deadline monitoring step.
Regards,
Purvesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Is it possible that i can know more on this?
Thanks in advance
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
go thru the Help.sap.com for "Deadline Monitoring " info.
In your case, what's happening is, when the deadline(Latest End,Req.End etc.,), they might be "Setting witems to Obsolete" by which the expired witems in the original intended agents were take out(Thru a "Process Ctrl" step) and in the Outcome of "Processing Obsolete" branch, you might be sending the same task to another set of users.
Once you go thru the help on "Deadline Monitoring " , you should be able to understand what i am talking about.
Hope this helps
venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi..
See the Below Link.
Regards,
Surjith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.