SCENARIO
I have two company code, each having separete plant .
Comapany Code A , Plant A
Company Code B, Plant B.
Now Plant A supplies raw material to Plant B, which after doing processing will give back to plant A.
this Senifinish material after processing at plant A gives finish assembly.
Can i plan these two plant in One Planning stage . (MRP at Plant A).
If not what can i do to transfer the requirenement to PLant B, after MRP run at Plant A.
Note: Its different company code.Spl pro Key 40,70,80 not work.
please suggest
Thnks in advance
Hi,
I have the same question. I'm new here. How did you solve it? Could you tell me?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!,
Please go through the following link
http://help.sap.com/saphelp_erp60_sp/helpdata/en/4d/2b90dc43ad11d189410000e829fbbd/frameset.htm
and check for Stock Transport Order with Delivery and Billing Document/Invoice (Cross-Company-Code). I think you might have missed some setting otherwise it must work. I have already used this fuctionality.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!,
You can work with special procurement keys even if you have plants in two different company codes. From PP angle there won't be any differnce in functionality but in FI / SD / MM intercompany transfers are treated as normal sales / purchase with the only diff that the GR will be made in the receiving plant with reference to delivery and not with ref to PO.
Regards,
Uday
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thkx for your reply.
I had already tried it..spl pro key not working in two plantof dif company code..when i m gng to use the key system ask me to cretae material in second plant though i had cretaed that material in second plant which is different company code.....so i writen its not work..
any other solution...please let me know..
thnaks
Thkx for your reply.
I had already tried it..spl pro key not working in two plantof dif company code..when i m gng to use the key system ask me to cretae material in second plant though i had cretaed that material in second plant which is different company code.....so i writen its not work..
any other solution...please let me know..
thnaks
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.